Pajaro River
Flood Risk Management Project
About the Project
The Pajaro River Flood Risk Management Project – a $599 million effort to reduce flood risk from the lower Pajaro River and Corralitos and Salsipuedes Creeks -- will provide 100-year flood protection to the City of Watsonville and the town of Pajaro, and a mix of 100-year and 25-year flood protection to the surrounding agricultural areas. The US Army Corps of Engineers and the CA Department of Water Resources will pay 100 percent of all project costs. However, the community is required to pay for ongoing operations and maintenance of the levee system.
First Increment of Construction: Reach 6 - Corralitos Creek
The Reach 6 project involves constructing new setback levees along Corralitos Creek from Green Valley Road to E. Lake Avenue/Highway 152. The project is underway, starting with vegetation removal and utility relocations. Civil construction can take place year-round, weather permitting, because new levees are being constructed where currently none exist. See Project Documents section below for Reach 6 design plans.
Project Fact Sheet
Project Need
Levees protecting the City of Watsonville, the town of Pajaro and surrounding agricultural areas are critically deficient. Today, these levees only provide an 8-year level of flood protection, among the lowest of any federal flood control project in California. At a minimum, 100-year flood protection is required to provide adequate flood protection for these disadvantaged communities and comply with federal regulations.
Project Documents
Relocation Plan for the Pajaro River Flood Risk Management Project - Reach 6 - December 2023
PLAN DE REUBICACIÓN PARA FOR THE PAJARO RIVER FLOOD RISK MANAGEMENT PROJECT – REACH 6 - Diciembre 2023
USACE Director’s Report — Pajaro River Flood Risk Management Feasibility Study — December 2019
USACE Report Summary: Pajaro River General Reevaluation Report, California — February 2019
USACE Director’s Report - Pajaro River Flood Risk Management Final General Reevaluation Report & Environmental Assessment — February 2019